Overhead electrical lines exceeding AC 1 kV - National Normative Aspects (NNA) for Slovenia (based on EN 50341-1:2012)
A new overhead power line is defined as a functionally completed installation for the
transmission of electricity between points A and B (i.e. the new construction of all
conductors, their supports together with foundations, earthing system, insulators,
accessories and fittings).
The overhead lines currently being designed (starting of a design to obtain a building
permit) or being under construction may be completed in accordance with the standards
in force at the time of the start of the design or construction of the overhead line.
In the case of maintenance and renovation works with major structural changes to
overhead lines, this standard shall be applied in accordance with the project
specification. E.g., for the construction of new support on new foundations in the existing
overhead line, the provisions of this standard shall be applied to support and foundations
but for the other elements of the overhead line don’t need to be complied with this
standard.
For the design and construction of DC overhead lines, the requirements of this standard
are also applicable to the design of structures, but not for electrical requirements, which
have to be specified in the project specification.
ΚΩΔΙΚΟΣ ΠΡΟΪΟΝΤΟΣ:
CYS EN 50341-2-21:2023
A new overhead power line is defined as a functionally completed installation for the
transmission of electricity between points A and B (i.e. the new construction of all
conductors, their supports together with foundations, earthing system, insulators,
accessories and fittings).
The overhead lines currently being designed (starting of a design to obtain a building
permit) or being under construction may be completed in accordance with the standards
in force at the time of the start of the design or construction of the overhead line.
In the case of maintenance and renovation works with major structural changes to
overhead lines, this standard shall be applied in accordance with the project
specification. E.g., for the construction of new support on new foundations in the existing
overhead line, the provisions of this standard shall be applied to support and foundations
but for the other elements of the overhead line don’t need to be complied with this
standard.
For the design and construction of DC overhead lines, the requirements of this standard
are also applicable to the design of structures, but not for electrical requirements, which
have to be specified in the project specification.